YNAG Jin,ZHAO Xueyuan,JIN XuesongCitation:.Case sharing and exploration of renovation and upgrading models for UPS maintenance in old hospital information machine rooms[J].Beijing Biomedical Engineering,2026,45(4):399-403.
YNAG Jin,ZHAO Xueyuan,JIN XuesongCitation:.Case sharing and exploration of renovation and upgrading models for UPS maintenance in old hospital information machine rooms[J].Beijing Biomedical Engineering,2026,45(4):399-403.DOI: 10.3969/j.issn.1002-3208.2026.04.010.
Case sharing and exploration of renovation and upgrading models for UPS maintenance in old hospital information machine rooms
This paper addresses the prevalent architectural flaws (e.g., lack of a maintenance bypass, failure of parallel redundancy) and operational risks of uninterruptible power supply (UPS) systems in aging hospital information rooms. It aims to explore effective models for emergency troubleshooting and systematic upgrades without interrupting core business operations.
Methods
2
First, a literature review was conducted to summarize UPS classifications and parallel configurations, identifying key risk points in legacy systems. Second, taking an extreme case of a hospital’s early-stage, non-maintenance-bypass, single-output parallel UPS system on the verge of collapse, a quantitative risk assessment method was applied. A combined strategy of “load reduction, isolation, and hot-swapping” was adopted. Key technical steps included implementing split load reduction using server dual-power supply characteristics, creating a bypass voltage following condition using a common utility power source, and employing an “in-phase voltage differential grid-connection method” for live replacement. Finally, based on the emergency experience, a low-cost, high-impact phased renovation plan was designed.
Results
2
The emergency live replacement of the faulty UPS was successfully accomplished with zero downtime for critical operational loads. The proposed subsequent renovation plan, which included installing independent circuit breakers at UPS input/output ends, adding a maintenance bypass, and laying a backup utility power line, could significantly enhance system reliability, safety, and maintainability at a relatively low cost.
Conclusions
2
The “risk-controlled emergency live replacement method” and the “low-cost phased renovation framework” proposed in this study provide a complete solution ranging from emergency response to systematic optimization for medical institutions facing similar challenges with aging physical infrastructure. This model holds certain value for broader application.
Wang CJ. Discussion on capacity expansion and transformation of UPS system in data center computer room[J]. Computer Knowledge and Technology, 2021, 17(12): 229-230.
Wang DS, Dai JR, Cai J, et al. The safety management and countermeasure study for UPS of hospital based on risk control[J]. China Medical Equipment, 2018, 15(6): 137-140.
Bu GX, Wang J, Guo CG, et al. Discussion on key issues in UPS selection, operation and maintenance in general hospitals[J]. Chinese Hospital Architecture & Equipment, 2024, 25(3): 45-49.